Someone on your side of the table.

Flagship Practice is an owner's representative for dentists building new practices. We manage the budget, the design and the contractors from site selection through opening day, so you can keep producing.

PMP certified Jacksonville, Florida Available nationally
The problem01

Everyone at the table has an incentive. None of them are yours.

The general contractor
Profits when scope grows. Every change order is revenue on a job they have already won.
The landlord
Wrote the lease and set the tenant improvement allowance. Their delivery condition decides how much of the build you pay for.
The equipment rep
Is paid on what you buy, not on whether it fits the space, the power plan or the schedule.
The lender
Wants the loan to close. Protecting your contingency after closing is not their job.

You are the least experienced person in the room, and the only one signing every check.

Definition02

An owner's rep is the one person on the job who only works for you.

No vendor commissions. No general contractor affiliation. No landlord relationships to protect. We sit in your seat at every Owner-Architect-Contractor meeting, review every pay application before it gets paid, and defend the budget you set at the start.

Ten workstreams, one accountable person.

01

Site and demographic strategy

Trade area analysis, site evaluation, test fits.

02

Lease and TI coordination

Models allowance and delivery condition against budget. Flags issues for your broker and attorney.

03

Budget development

Full project pro forma: hard costs, soft costs, FF&E, contingency.

04

Design and 3D visualization

Space planning, finish direction, photoreal renders of your practice.

05

Team procurement

Architect, engineer and GC bidding, leveling and contract administration.

06

Permitting and approvals

City, health department and radiation shielding compliance.

07

Construction oversight

OAC meetings, pay application review, change order defense, quality walks.

08

Equipment and technology

Chairs, imaging, sterilization, IT and low voltage coordination.

09

Vendor and FF&E logistics

Procurement schedule, delivery sequencing, install supervision.

10

Closeout and opening

Punch list, certificate of occupancy, warranties, owner training, day one readiness.

The numbers03

What a dental buildout really costs.

$150–$400
Per square foot

Dental tenant improvement is among the most expensive TI categories in commercial real estate.

$225K–$675K
Four-operatory build

Construction alone, before equipment. Ground-up and larger projects run $700K to $1.1M.

16–28 wks
Permit to CO

Equipment coordination usually drives the critical path, not framing or finishes.

10–12 mo
Engagement to opening

Typical project. Phases overlap by design, because schedule compression is the product.

$0 $300K $600K $900K $1.2M 4 operatories, tenant improvement 6,000+ SF, ground-up or multi-suite $225K–$675K $700K–$1.1M
Construction cost only. Equipment, FF&E, soft costs and working capital sit on top of these figures. Industry planning assumes a 10 to 15 percent contingency, and change orders, permit delays and equipment coordination misses are what consume it.
Schedule04

Five phases from vision to opening day.

Phases overlap deliberately. Design starts before the program is fully closed, bidding starts before permit comment is back, and equipment ordering starts long before anyone thinks it needs to. That overlap is where the months come from.

WK 0 8 16 24 32 40 48 Chart Design Assemble Build Launch WK 1–6 WK 4–12 WK 10–20 WK 20–44 WK 44–48 OPENING DAY
Typical tenant improvement engagement, roughly 10 to 12 months from signature to opening. Ground-up projects run longer. Week ranges are planning figures, not a promise on any specific project.
See the full process
Fit05

Built for the first-time practice owner.

You are buying or leasing space for a startup practice, relocating an existing one, or expanding into a second location. You have a lender, an accountant and probably a broker. What you do not have is anyone whose only job is making sure the build comes in on budget and opens on time.

If you have already built three practices and have a contractor you trust, you probably do not need us.

Why Flagship06

Four things that are true on day one.

Credential

PMP certified

Formal project management certification layered on twelve years of applied schedule, cost and risk management.

Background

Deadline DNA

A decade running event and fabrication builds, where the open date never moves. Backward scheduling and vendor orchestration are exactly what a practice opening demands.

Capability

See it before you build it

In-house 3D rendering and space planning. You approve a room you have already walked through digitally, and your lender sees a fundable vision rather than a line item.

Incentives

Fixed fees, never a percentage

Our fee is set by scope at engagement and never grows because your budget did. Percentage-fee representatives earn more when your project costs more. That is a conflict of interest, not a fee model.

Next step07

Start with the numbers.

Book a free budget snapshot. Bring whatever you have, a listing, a lease draft or a napkin sketch, and we will walk through a realistic cost range for a practice your size and how long it takes to open.

No obligation. No deliverable. No pitch.

Book a free budget snapshot